Published On
10/10/2022Local sporting associations and clubs, as well as the wider community will benefit from an $11million project which will upgrade 16 sportsgrounds across the Central Coast region.
This NSW Government funded project will deliver improved facilities that encourage participation in sport and support healthy and active lifestyles for our community.
The works consists of various sports infrastructure upgrades, such as the installation of sports lighting, drainage and irrigation; which will allow for increased use of the grounds throughout the year and improved safety for players and supporters.
As part of this project, works will be undertaken at the Central Coast Regional Sports and Recreation Complex at Tuggerah, to upgrade Premier Field 5 (drainage, irrigation, and re-levelling), construct hard surface courts to Central Park, and to install ball net fencing, a wash down bay, entry signage and event storage. These upgrades will enhance this quality facility’s current offerings and further attract elite sports and visitors to our region.
Upgrade works are also planned for sports grounds at Blue Haven (Blue Haven Oval), Buff Point (Buff Point Oval), East Gosford (Hylton Moore Oval), Holgate (Paul Oval), Kariong (Kariong Oval), Kincumber (Patrick Croke Oval), Narara (Paddy Clifton Oval and Carrington/Pandala Oval), Noraville (Darren Kennedy Oval), Ourimbah (Sohier Park), San Remo (Northlakes Oval), Tacoma (Don Small Oval), Terrigal (Terrigal BMX facility), and Wyoming (Maidens Brush Oval and Alan Davidson Oval).
High Quality drainage and irrigation systems at sports fields play an important role in facilitating quicker wear recovery, maintaining healthier turf all year round and enabling grounds to re-open faster after wet weather events. These works will improve the quality of the fields, making it more enjoyable to play on, limiting field closure and interruptions to seasons. This means our sporting community can get back on the field quicker after wet weather and play the sports they love.
Effective sports lighting increases the use of a sporting facility for play and training, whilst creating a safe and enjoyable facility for competitors and spectators – especially during winter seasons when it’s dark by late afternoon.
This project is proudly funded by the NSW Government.
Central Coast Council is working with Public Works Advisory (PWA) to deliver the works associated with this project.
This project works schedule commenced late 2021, with completion of works at all sites expected by December 2022 (weather permitting).
For enquiries on this project, please contact Council’s project team by email openspace.projects@centralcoast.nsw.gov.au
project works schedule
(updated: December 2022)
Suburb | Sports Oval | Planned works | Start date | Expected end date (weather dependant) | Notes |
---|---|---|---|---|---|
Blue Haven | Blue Haven Oval | Drainage and irrigation | 26 April 2022 | 31 January 2023 | Works underway. Playing field is closed for use |
Buff Point | Buff Point Oval | Sports lighting | 17 January 2022 | 30 October 2022 | On field works complete and night testing has been undertaken. Final implementation is in progress. |
East Gosford | Hylton Moore Oval | Sports lighting to Field 1 | 24 January 2022 | complete | On field works complete and night testing has been undertaken. Final implementation is in progress. |
Holgate | Paul Oval | Levelling of playing surface, drainage and irrigation | 24 November 2021 | 13 January 2023 | works underway Playing field is closed for use Ball fence and cricket net upgrade works complete |
Kariong | Kariong Oval | Sports lighting | 7 February 2022 | complete | On field works complete and night testing has been undertaken. Final implementation is in progress. |
Kincumber | Patrick Croke Oval | Sports lighting | May 2022 | complete | On field works complete and night testing has been undertaken. Final implementation is in progress. |
Narara | Paddy Clifton Oval | Drainage and irrigation | 4 July 2022 | 28 February 2023 | Works underway. Playing field is closed for use. |
Narara | Carrington/ Pandala Oval | Field expansion including retaining wall construction and vegetation removal, regrading of a portion of the playing surface, construction of a new turf wicket, drainage & irrigation | 24 January 2022 | 28 February 2023 | Works underway. Playing field and the southern portion of the carpark is closed for use. |
Noraville | Darren Kennedy Oval | Drainage and irrigation | 30 November 2021 | complete | All works complete. Site Open for use. |
Ourimbah | Sohier Park | Drainage and irrigation | 21 March 2022 | 31 January 2023 | works underway. Playing field is closed for use. |
San Remo | Northlakes Oval | Drainage and irrigation | 12 September 2022 | 28 February 2023 | works underway. Playing field is closed for use. |
Tacoma | Don Small Oval | Drainage and irrigation | 6 April 2022 | 13 January 2023 | Works underway Playing field is closed for use. |
Terrigal | Terrigal BMX | Sport lighting | 21 February 2022 | complete | Perimeter works completed and night testing has been undertaken. Final implementation is in progress. |
Tuggerah | Central Coast Regional Sports and Recreation Complex | Upgrades to Premier Field 5 (drainage, irrigation, and re-levelling), construction of hard surface courts to Central Park, installation of ball net fencing, wash down bay and new LED entry signage | December 2021 | complete | Works complete. |
Wyoming | Maidens Brush Oval | Regrading of playing surface, drainage and irrigation and sports lighting | 15 January 2022 | 3 January 2023 | Works complete. |
Wyoming | Alan Davidson Oval | Sports lighting installation on fields 1 and 4. | 10 January 2022 | complete | On field works complete and night testing has been undertaken. Final implementation is in progress. |
*for any sites receiving drainage and irrigation upgrades, the grounds will be closed an additional month after construction works are complete. This is to allow time for the turf to grow over the trench lines created by excavation for the drainage and irrigation pipework, which will ensure player safety. This additional time is included in the dates provided in the table above.
Council remains committed to providing and maintaining quality sports facilities for the benefits they provide to our community. In addition to this project Council is undertaking several additional projects to improve sport and recreation facilities region-wide. Follow Council’s social media pages and eNews for updates.
To keep up to date with Council news subscribe to eNews and follow our social media pages.
Frequently Asked Questions
Can the grounds be used during whilst works are underway?
The facilities that are having drainage and irrigation upgrades will be closed for use while the works are underway. The facilities where floodlighting works are being undertaken can still be used, with only areas around the perimeter of the Fields being closed. Please refer to the project works schedule for the full list of facilities and works being undertaken at each.
How do these works impact organised sports?
The facilities that are having drainage and irrigation upgrades will be closed for use while the works are underway, therefore the clubs who would generally utilise these grounds will be relocated for training and games during this period. Council is working closely with each of the Central Coast sporting associations to communicate the project program and reallocate grounds. The facilities where floodlighting works are being undertaken can still be used, meaning that the clubs who would generally utilise these grounds will still have access to them for training and games.
What are the benefits of the works being undertaken?
High Quality drainage and irrigation systems at sports fields play an important role in facilitating quicker wear recovery, maintaining healthier turf all year round and enabling grounds to re-open faster after wet weather events. These works will improve the quality of the fields, making it more enjoyable to play on, limiting field closure and interruptions to seasons. This means our sporting community can get back on the field quicker after wet weather and play the sports they love.
Effective sports lighting increases the use of a sporting facility for play and training, whilst creating a safe and enjoyable facility for competitors and spectators – especially during winter seasons when it’s dark by late afternoon.